Once the
preparation of Test Case Development and Test Environment setup is completed
then test execution phase can be kicked off. In this phase testing team start
executing test cases based on prepared test planning & prepared test cases
in the prior step.
Once the
test case is passed then same can be marked as Passed. If any test case is
failed then corresponding defect can be reported to developer team via bug
tracking system & bug can be linked for corresponding test case for further
analysis. Ideally every failed test case should be associated with at least
single bug. Using this linking we can get the failed test case with bug
associated with it. Once the bug fixed by development team then same test case
can be executed based on your test planning.
If any of
the test cases are blocked due to any defect then such test cases can be marked
as Blocked, so we can get the report based on how many test cases passed,
failed, blocked or not run etc. Once the defects are fixed, same Failed or Blocked
test cases can be executed again to retest the functionality.
|
Entry
Criteria
|
Activities
|
Deliverable
|
|
2. Test
cases.
3. Test
data.
|
1.
Based
on test planning execute the test cases.
2. Mark status of test cases like Passed, Failed,
Blocked, Not Run etc.
3. Assign Bug Id for all Failed and Blocked test
cases.
4. Do Retesting once the defects are fixed.
5. Track the defects to closure.
|
1.
Test
case execution report.
2. Defect report.
|